Expansion of water treatment technology in the Zakład Wodociągu Praskiego in Warsaw (WTP Praga)
04.09.2015
Start-up of ozone and activated carbon filter installations in WTP Praga
The Start-up period has begun on April 30, 2015. Successfully and at the scheduled dates all mechanical and hydraulic start-up stages were completed. From July 14, 2015 the Seen Technologie commissioning team under the direction of Mr. Bogdan Walczuk entered the technological start-up phase. Currently, we have filled up with granulated activated carbon 7 of 10 filter chambers. On August 11, 2015 we have received the permit of the Orderer to start the production of water to the municipal network from the first 3 carbon filters. Up to the present day we have already run out 6 of carbon filters, which produce water for clean water tanks. With a new production line, we achieve a capacity of 36,000m3/day, which is more than half of the average daily water production of WTP Praga.